Construction Timelines: What to Know Before You Build

Chuck Liss • 4 February 2014

Article by:

One of the first questions we get when talking to clients about a new custom home or remodel is, “How much will it cost?” This is usually quickly followed by the second question, “How long will it take?” The answer to both is, “It depends.” 

While we don’t want to be evasive, there are many variables that have to be factored in before we can adequately assess the time and cost of a project. One thing that most homeowners don’t see initially is that for a properly planned and designed project, the design and construction phases can last roughly the same amount of time.

As I’ve written about previously, the  design process  can take up to six to eight months for a new custom build (including determining the client’s needs, designing to those needs and deciding how to best to build the project). And it could take longer if there are complications such as other approvals or if someone objects to your project. This time is not spent just daydreaming and staring out the window — your team is working to understand the design and construction to smooth out potential issues in your timeline.  

Be realistic.  It’s often difficult for homeowners to know what’s realistic for each phase of the construction process. For instance, one week to construct a kitchen is not realistic due to the number of services and trades involved — installers, plumbers, tile contractors. It would be foolhardy to think that everything could be done to satisfaction in such a short time. 

What’s also confusing is that timelines for suburban developments can be wildly different from a single luxury custom home. We have had clients ask us why a custom home costs more per square foot and takes longer that a tract home. The reason is that developers have crews that move from house to house and are dedicated to that development. This means that for all intents and purposes, they finish their work on one house and move on to the next. 

On a custom house, your framers might be a week late showing up (because their last job ran late), and then the next trade in line is thrown off as well. You can see how this can cause a domino effect on your project. Most contractors can’t wait around until the exact time they are needed on a site — they have to keep their crews busy, or they don’t get paid. So they tend to overbook rather than underbook to make sure they have enough work to keep them busy.  

Often one trade cannot begin work until another is finished. There is time associated with mobilization and demobilization of each trade, and often one of the trades cannot be onsite the exact day or even within a week of when you need it. So often there is downtime that needs to be accounted for. When planning, it is important not to try to plan schedules too tightly, as they rarely work out that way.

Understand the timeline and the implications of what is written.  Do you know what demolition entails? The mess? The noise? Words on a spreadsheet can seem awfully abstract when you are looking at them in your living room, but they can mean a whole different thing when one wall of your kitchen is blown out in the middle of a March storm. It might mean that you want to  consider moving out  while some of the more disruptive work is completed. Your design team should be helping determine this as part of their work. If you don’t understand what specific items mean, clarify them with your team. 

Also, plan for construction to take place when it will best for the project and affect your family the least. One of our clients learned the hard way after he insisted on starting a project just as winter set in. The contractors were only able to pour the footings, and then a cold snap set in, which held up the project for six weeks. The lesson here is to understand what potential delays could crop up that could derail your project timeline.  

What is in the timeline?  Your timeline should be specific enough to include a level of detail that helps you and your team understand the logical flow of activities, so you can follow the logical steps that should happen in sequence. It is typical to require the contractor, as part of the contract, to prepare a comprehensive schedule for all work and phases from start to finish and present it at the beginning of the project. This schedule is then reviewed at a start-up meeting, at which the client, architect, contractor and major consultants who might have a stake are present.  

Get a sense of what could affect the timeline.  There’s a rule of thumb for construction used by contractors and designers: “It will always take longer than you think.” There are a number of factors that conspire against the pristine order of a freshly minted timeline document: complexity, weather, number of construction workers, permits and inspections, back orders and delays for materials, equipment or fixtures. Make sure you or your team members are aware of products that have a long lead time. These could include materials, equipment or products that are not warehoused locally, such as custom-fabricated furniture, light fixtures or imported tile. 

There are also municipal approvals to consider. A municipal building inspector has to come to the site during construction to check that what is being built corresponds with the drawings. It is the contractor who coordinates these inspections, and who needs to plan for them so work doesn’t stop while everyone waits for an inspection to happen. 

If the inspector feels there is a gap between what has been documented in the drawings and what is being built, he or she can request more information from the team. This is to understand that the changes from what is documented in the drawings will still satisfy the building code. Or worse, the inspector can place a stop-work order, which effectively shuts down the project. And that can put your timeline on life support. But with proper project oversight from your design team, your project should be able to move along smoothly.  

Final details.  For some reason the final details on a project often take a lot longer that you might think. The reasons are that they often require very precise work that takes time to get right. Things like installing trim or custom millwork can wreak havoc on a schedule. 

On a recent project, we specified a custom millwork piece for all the bathrooms. The challenge was that it required coordinating three separate trades: the millworker who built the cabinets, the countertop contractor who fabricated the quartz and the stainless steel fabricator who made the custom sink. While the owner is thrilled with how it looks, it did take some time to get everyone involved on the same page. 

One thing to keep in mind is that at the end of the project, most of the budget has been spent and many of the tradespeople have made the majority of their money. This is where holdbacks come in. A holdback keeps a certain percentage of the contract amount set aside until a set number of days after completion. Tradespeople want to see their work completed and will finish up what needs to be done. But in some cases, it is important to not only judge the amount of work done when a contractor applies to be paid but also how much work is left, and can the remaining funds motivate them to finish. It is not unheard of for a designer to return a contractor’s application for payment and insist that certain details are done first before the requested amount is paid out.  

Just as there is not one piece of art that everyone agrees is perfect, there is no construction timeline that fits all projects. But by  working with your team , you can understand the components that go into your timeline. And that can help avoid timeline trauma during construction.

Accredited Stone Fabricator - Natural Stone Institute
by Bryan Bean 30 August 2023
We are thrilled to announce that The Top Shop, Inc. has achieved a prestigious milestone in the world of natural stone craftsmanship – we are now an Accredited Natural Stone Fabricator, as designated by the esteemed Natural Stone Institute. This recognition underscores our dedication to quality and expertise in the fabrication and installation of natural ... Read more The post The Top Shop INC Earns Fabricator Accreditation From Natural Stone Institute first appeared on The Top Shop Inc..
by Bryan Bean 25 May 2023
When it comes to kitchen remodeling, choosing the right countertops can make all the difference. With so many options available, it can be overwhelming to decide which materials to use. However, if you’re looking for a durable, low-maintenance option, granite countertops are the way to go. Not only do they add a touch of elegance ... Read more The post 4 Benefits of Choosing Granite Countertops for Your Kitchen first appeared on The Top Shop Inc..
by Bryan Bean 1 May 2023
Let's take a closer look at the benefits of installing quartz countertops in your home, and why they might be the perfect choice for your kitchen or bathroom renovation. The post The Benefits of Installing Quartz Countertops in Your Home first appeared on The Top Shop Inc..
by Bryan Bean 26 April 2023
You could win a brand new home in Colorado Springs and with the 2023 St. Jude Dream Home Giveaway! We are proud to once again be a trade partner working with Covington Homes, who is building another Dream Home to benefit St. Jude Children’s Research Hospital. We’ll be installing some absolutely beautiful countertops in the ... Read more The post Win the 2023 St. Jude Dream Home Giveaway in Colorado Springs first appeared on The Top Shop Inc..
by Bryan Bean 5 April 2023
Used as the first building blocks known to humankind, natural stone continues to captivate and inspire us in the present day. Its enduring popularity stems from its remarkable strength, durability, and an exquisite array of colors, patterns, and finishes. Join us on a journey to discover fascinating facts about this ancient treasure that will ignite ... Read more The post Facts About Natural Stone first appeared on The Top Shop Inc..
by Bryan Bean 3 April 2023
Natural stone countertops have been a popular choice for homeowners for decades. These countertops are not only beautiful but also durable, making them a practical and long-lasting investment for any home. From classic marble to stunning granite, there are various types of natural stone that can add elegance and value to your kitchen or bathroom. ... Read more The post Types of Natural Stone for Home Countertops: A Comprehensive Guide first appeared on The Top Shop Inc..
by Bryan Bean 1 February 2023
So, you got new painted cabinetry and it looks amazing. What needs to be done to keep your cabinets looking great for years to come? Let’s take a look at some cleaning and maintenance you can do to keep your cabinets looking new, as well as a few things you can expect from painted cabinets ... Read more The post How To Care for Painted Cabinets first appeared on The Top Shop Inc..
by Bryan Bean 25 November 2022
The Shop Small movement has become a shopping tradition for many. It’s an opportunity to share your support for small businesses with roots in our community. We started as a small 6-person laminate shop in Arvada, and have grow, moved our showroom to Denver, and now employ dozens of hard-working Coloradans, all thanks to the ... Read more The post Shop Small And Support Local Denver Businesses first appeared on The Top Shop Inc..
by Bryan Bean 1 November 2022
Engineered quartz countertops rival stone in their look and performance, but often require far less maintenance. There are some easy steps you can take to clean quartz counters. The are also a few things you need to avoid, like using abrasives or acid/alkaline cleaners like acetone, which can cause damage to your countertops. Engineered quartz ... Read more The post How To Clean Quartz Counters first appeared on The Top Shop Inc..
by Bryan Bean 1 June 2022
Can’t decide between natural wood and painted kitchen cabinets? It doesn’t have to be either/or. Many designers are mixing cabinet colors rather than matching. The post 5 Tips for Mixing Cabinet Colors first appeared on The Top Shop Inc..
More posts
Share by: